Back to Search Start Over

Construction and Commissioning of the KSTAR Helium Distribution System.

Authors :
Lee, Y. J.
Park, Y. M.
Kim, Y. S.
Jang, H. S.
Kwag, S. W.
Chang, Y. B.
Park, H. T.
Woo, I. S.
Song, N. H.
Bang, E. N.
Ha, T. H.
Baek, S.
Kim, M. K.
Kim, W. C.
Oh, Y. K.
Bak, J. S.
Source :
IEEE Transactions on Applied Superconductivity. Jun2009 Part 2 of 3, Vol. 19 Issue 3, p1582-1586. 5p. 5 Charts, 2 Graphs.
Publication Year :
2009

Abstract

The KSTAR components requiring cryogenic helium coolant for superconducting magnet operations are connected to the helium refrigeration system (HRS) through the helium distribution system (HDS), the final helium distribution station. Twenty eight cryogenic valves including 4 quench protecting valves, many sensors such as temperature sensors, pressure transmitters, and flowmeters are mounted on the system. The HDS has to control the 4.5 K supercritical helium (600 g/s) for 30 superconducting coils and their superconducting bus-lines, 55 K helium (270 g/s) pressurized to 18 bars for the thermal shields and the gravity supports, and a maximum 17.5 g/s of liquid helium for 18 current leads, provided from the HRS which has a 4.5 K equivalent cooling power of 9kW. The helium distribution system consists of a helium distribution box (DB), 5 helium transfer lines, a PLC based helium control system (HCS), etc. The helium control system is connected to the KSTAR supervisory control & interlock system. The detailed status regarding the construction, commissioning during first cool-down, and the instrumentation & control (I&C) system are included in this paper. [ABSTRACT FROM AUTHOR]

Details

Language :
English
ISSN :
10518223
Volume :
19
Issue :
3
Database :
Academic Search Index
Journal :
IEEE Transactions on Applied Superconductivity
Publication Type :
Academic Journal
Accession number :
43923786
Full Text :
https://doi.org/10.1109/TASC.2009.2018239