BIM-Based Co-Simulation of Fire and Occupants' Behavior for Safe Construction Rehabilitation Planning.

Authors :
Abadi, Seyedeh Tannaz Shams
Tokmehdash, Nojan Moniri
Hosny, Abdelhady
Nik-Bakht, Mazdak
Source :
Fire (2571-6255); Dec2021, Vol. 4 Issue 4, p1-28, 28p
Publication Year :
2021

Abstract

Construction renovation projects increase the risk of structural fire, mostly due to the accumulation of combustible construction materials and waste. In particular, when the building remains operational during such projects, the redistribution of occupants and interruptions with access corridors/exit egress can exponentially increase the risk for the occupants. Most construction projects are, however, planned and scheduled merely based on the time and budget criteria. While safety is considered paramount and is meant to be applied as a hard constraint in the scheduling stage, in practice, safe evacuation considerations are reduced to rules of thumb and general code guidelines. In this paper, we propose simulation as a tool to introduce safety under structural fire, as a decision criterion, to be mixed with time and budget for selecting the best construction schedule alternative. We have used the BIM (building information model) to extract the building's spatial and physical properties; and have applied co-simulation of fire, through computational fluid dynamics (CFD), and occupants' evacuation behavior, through agent-based modeling (ABM) to estimate the average and maximum required safe egress time for various construction sequencing alternatives. This parameter is then used as a third decision criterion, combined with the project's cost and duration, to evaluate construction schedule alternatives. We applied our method to a three-floor fire zone in a high-rise educational building in Montreal, and our results show that considering the fire safety criterion can make a difference in the final construction schedule. Our proposed method suggests an additional metric for evaluating renovation projects' construction plans, particularly in congested buildings which need to remain fully or partially operational during the renovation. Thus, this method can be employed by safety officers and facility managers, as well as construction project planners to guide accounting for fire incidents while planning for these types of projects. [ABSTRACT FROM AUTHOR]

Details

Language :
English
ISSN :
25716255
Volume :
4
Issue :
4
Database :
Complementary Index
Journal :
Fire (2571-6255)
Publication Type :
Academic Journal
Accession number :
154410608
Full Text :
https://doi.org/10.3390/fire4040067