A Project-Scheduling and Resource Management Heuristic Algorithm in the Construction of Combined Cycle Power Plant Projects.
- Source :
- Computers (2073-431X); Feb2022, Vol. 11 Issue 2, p23, 1p
- Publication Year :
- 2022
-
Abstract
- Given the growing number of development projects, proper project planning and management are crucial. The purpose of this paper is to introduce a heuristic algorithm for scheduling a power plant project construction and project resource management to determine the size of project buffers and feeding buffers. This algorithm consists of three steps: 1. estimating the duration of project activities; 2. determining the size of the project buffer and feeding buffers; and 3. simulating the mentioned algorithm, which will be explained below. Innovations of this research are as follows: estimating the exact duration of project activities by using a heuristic algorithm, in addition to determining the buffer size; calculating both project buffer and feeding buffers; and applying the algorithm to implement an ACC used in combined cycle power plant projects as a numerical example. In order to evaluate the proposed algorithm, inputs from this project were run through several algorithms recently presented. The results showed that a suitable amount of buffers can be allocated for projects using this algorithm. [ABSTRACT FROM AUTHOR]
Details
- Language :
- English
- ISSN :
- 2073431X
- Volume :
- 11
- Issue :
- 2
- Database :
- Complementary Index
- Journal :
- Computers (2073-431X)
- Publication Type :
- Academic Journal
- Accession number :
- 155708285
- Full Text :
- https://doi.org/10.3390/computers11020023