Back to Search Start Over

A two-stage stochastic programming approach for project planning with uncertain activity durations.

Authors :
Guidong Zhu
Jonathan Bard
Gang Yu
Source :
Journal of Scheduling; Jun2007, Vol. 10 Issue 3, p167-180, 14p
Publication Year :
2007

Abstract

Abstract   This paper investigates the problem of setting target finish times (due dates) for project activities with random durations. Using two-stage integer linear stochastic programming, target times are determined in the first stage followed by the development of a detailed project schedule in the second stage. The objective is to balance (1) the cost of project completion as a function of activity target times with (2) the expected penalty incurred by deviating from the specified values. It is shown that the results may be significantly different when deviations are considered, compared to when activities are scheduled as early as possible in the traditional way. For example, the optimal target completion time for a project may be greater than the makespan of the early-start schedules under any scenario. To find solutions, an exact algorithm is developed for the case without a budget constraint and is used as a part of a heuristic when crashing is permitted. All computational procedures are demonstrated on a set of 150 benchmark problems consisting of 90 activities each. [ABSTRACT FROM AUTHOR]

Details

Language :
English
ISSN :
10946136
Volume :
10
Issue :
3
Database :
Complementary Index
Journal :
Journal of Scheduling
Publication Type :
Academic Journal
Accession number :
25369051
Full Text :
https://doi.org/10.1007/s10951-007-0008-x