Commissioning of the first WEST load-resilient long pulse ICRF launcher in the TITAN testbed and on WEST plasmas
- Source :
- Fusion Engineering and Design. 146:1778-1781
- Publication Year :
- 2019
- Publisher :
- Elsevier BV, 2019.
-
Abstract
- Before the installation of the first ICRF launcher in WEST, dedicated RF, cold and hot leak tests have been performed in the TITAN test bed [ 1 , 2 ] (Bernard et al., 2011a,b). All the water circuits have been controlled in order to avoid any in-vessel leak. The impedance matching has been checked at low level (mW range) and the high RF voltage standoff has been validated at the nominal value of 27 kV peak. During the WEST C3a campaign, the commissioning of the first antenna has been successfully performed. About 0.6 MW of power has been coupled to the plasma, and the launcher’s load-resilience has been proved.
- Subjects :
- Leak
Mechanical Engineering
Nuclear engineering
Impedance matching
Plasma
01 natural sciences
010305 fluids & plasmas
Power (physics)
symbols.namesake
Nuclear Energy and Engineering
0103 physical sciences
symbols
Environmental science
General Materials Science
Antenna (radio)
010306 general physics
Titan (rocket family)
Civil and Structural Engineering
Electronic circuit
Voltage
Subjects
Details
- ISSN :
- 09203796
- Volume :
- 146
- Database :
- OpenAIRE
- Journal :
- Fusion Engineering and Design
- Accession number :
- edsair.doi...........16d4017c962fb47f7cc4492bbf8a10c0
- Full Text :
- https://doi.org/10.1016/j.fusengdes.2019.03.033