Back to Search Start Over

A method for quick evaluation of stepwise plant expansion scenarios in the chemical industry

Authors :
Axel Polt
Bernhard Krepinsky
Joost-Willem Snoeck
Georg Grossmann
Heinrich Terhorst
Thieu-Luan Hong
Martin Schlegel
Jan Ulrich
Jan Oldenburg
Publication Year :
2007
Publisher :
Elsevier, 2007.

Abstract

The profitability of investment projects for chemical production plants is affected by the installed plant capacity in relation to the actual sales of the materials produced in the plant. Especially for markets with large predicted growth rates, it can be beneficial to gradually increase the installed production capacity rather than building a large capacity at once. Whether this is the case, however, depends on various factors such as the product sales forecast and the technology, cost structure and economy of scale of the required production equipment. We propose a method which enables a quick comparison of possible stepwise plant expansion scenarios versus building a full capacity plant.

Details

Database :
OpenAIRE
Accession number :
edsair.doi...........ccaff87754693a60cd18d66354f316b5
Full Text :
https://doi.org/10.1016/s1570-7946(07)80117-9