Back to Search Start Over

An on-load test method prior to substation operation based on synchronous current and voltage output

Authors :
FANG Yudong
QIU Yutao
WANG Weidong
ZHANG Yunhua
WANG Junkang
XIANG Xin
CAO Wenbin
Source :
Zhejiang dianli, Vol 41, Iss 10, Pp 78-86 (2022)
Publication Year :
2022
Publisher :
zhejiang electric power, 2022.

Abstract

Given the limitations of the original primary current and voltage carrying tests prior to substation operation, the paper expounds the principle of high current and high voltage decoupling and synchronous output control and proposes an on-load test method prior to substation operation based on high current and high voltage decoupling and synchronous output, that is, by reasonable arrangement of the state of the primary equipment under test, the testing current and voltage can normally pass through components to be tested such as TA and TV, and then the analog on-load test is completed by discriminating the recovery signal. The paper also introduces test schemes under different wiring modes and voltage classes. The engineering case shows that this method can fully meet the test requirements of substation with voltage levels of 500 kV and below prior to operation and ensure the correct and efficient circuit check before substation operation.

Details

Language :
Chinese
ISSN :
10071881
Volume :
41
Issue :
10
Database :
Directory of Open Access Journals
Journal :
Zhejiang dianli
Publication Type :
Academic Journal
Accession number :
edsdoj.fac9b44b779e4a26a09a5aefa1bde6f3
Document Type :
article
Full Text :
https://doi.org/10.19585/j.zjdl.202210011