Optimization of Start-Up of a Fully Fired Combined-Cycle Plant with GT13E2 Gas Turbine

Authors :
A. G. Anisimov
A. R. Gevorgyan
S. Kh. Eritsyan
G. S. Petrosyan
M. V. Klub
A. V. Avtandilyan
K. B. Sargsyan
Source :
Power Technology and Engineering. 49:359-364
Publication Year :
2016
Publisher :
Springer Science and Business Media LLC, 2016.

Abstract

The principles of starting up the steam power unit of the Hrazdan-5 fully fired combined-cycle power unit (Hrazdan, Armenia) are considered. This plant has neither a bypass stack for gas discharge from the gas turbine nor an external steam source for the steam-turbine gland and prestarting deaeration. Emphasis is placed on the differences between the start-up procedure followed at the plant and the procedure provided by the RD 34.25.512 Standard Instructions on Startup from Various Thermal States and Shutdown of 300-MW Boiler-Turbine Sets with K-300-240 LMZ Turbine.

Details

ISSN :
15701468 and 1570145X
Volume :
49
Database :
OpenAIRE
Journal :
Power Technology and Engineering
Accession number :
edsair.doi...........5f43f8e6f4995d98c447911795a5b5df
Full Text :
https://doi.org/10.1007/s10749-016-0628-4